Cafe Construction
February 13, 2022
We are Excited to Announce the Grand Opening of the Hampton Coffee Company Library Café!
February 12, 2022
January 18, 2022
Punch list items are being completed. Once inspections and permits are issued the cafe will be ready to open! The entrance to the Library from Montauk Highway has been opened.
December 29, 2021
Hampton Coffee is starting to move their equipment in! The Library relocated our Oversized Book collection next to an electric fireplace that was purchased as a gift from the Friends of the Library in the newly created lounge area. Keep checking back to our website for the latest information.
December 6, 2021
We are in the home stretch! Finishing touches are underway. Hampton Coffee has installed their sign and once all construction is complete, they will be bringing in their equipment. Keep checking back to our website for the latest information.
November 1, 2021
We have seen a lot of progress this last month and in the upcoming week we will be installing the sanitary system, backfilling the driveway, installing the HVAC unit on the roof top and installing the tile floor throughout the cafe and library hallway. Anticipated completion is just weeks away!
September 29th, 2021
The vestibule with automatic doors has been installed as well as the glass storefront. Electrical is almost complete. Installation of drywall and flooring are scheduled soon.
August 23, 2021
The walls and ceilings have been almost completely framed. The plumbing is roughed in and insulated. HVAC ductwork is in place. We are ready for the storefront, and then we can really start finishing construction!
July 20, 2021
The concrete floor has cured and the walls are being framed out. HVAC and duct work are being installed and plumbing is currently being worked on. The layout of the space is starting to take shape!
June 29, 2021
The concrete slab has been poured and interior plumbing and electrical work has begun. We are a few short months away from the anticipated completion date of mid October.
May 11, 2021
Work has been steady and we anticipate pouring foundation and replacing the walkways and curbs in the upcoming week. This past month our General Contractor, RENU constructed a temporary wall to serve as a barrier to reduce noise, dust and debris by the current computer area.
A temporary door that will later serve as a permanent emergency exit was installed in the Teen Area and trees were relocated on the property.
The Community Room closet has been constructed we await materials to finish off this portion of the project.
Sidewalks were removed as well as the existing concrete pad located under the canopy. Once soil testing is completed, footings and foundation will be poured.
4/13/2021
How the front of the building currently looks, before construction.
After almost three years of planning, the Library is excited to announce that construction on the Library Café will begin on April 14, 2021!
This expansion will create approximately 600 square feet of usable space under the existing canopy on the Southwest corner of the building. It will provide a comfortable area for patrons to sit and enjoy a cup of coffee or a snack while they read the paper, work on an assignment or converse with friends. This project also includes the creation of wider sidewalks on the West end of the building, modifying curbs on the West side of the parking lot, a permanent emergency exit out of the Teen area and the creation of a closet in our Community Room. Careful budgeting has allowed this project to proceed without asking the public taxpayer for additional funding for this Capital Project. The project was publicly bid and Renu contracting was awarded the project totaling $977,450.
The Library Café will be leased to Hampton Coffee Company and will offer a menu of homemade hot breakfast and lunch, coffee and espresso drinks, and lots of delicious bakery items–all baked right here at the Library!